When Nolensville activated its agreement with TDOT to fix the misaligned meeting of Williams Road and York Road at Nolensville Road, the Town sent the state a construction deposit of just under $720,000, as Williamson Scene reported at the time. The work was scheduled to wrap up in May 2026. Instead, final asphalt was scheduled for October 20 and 21, 2026, on roughly 500 feet of realigned road.
That slipping schedule explains the next ten years of driving in Nolensville. The project most people have in mind when they think about traffic on Nolensville Road is widening the road through town. Its construction is now set for 2036. Until then, the changes you'll actually see are intersections, one at a time. Each one gets held up first by something other than construction: utility poles, bid paperwork, right-of-way deals or a state funding cycle.
Why York and Williams kept slipping
The York/Williams/Nolensville Road project is a Town partnership with TDOT, which manages the work. Town Engineer Enoch Jarrell explained in an October 9 Town video that TDOT is shifting and rebuilding about 500 feet of Williams Road west toward the bridge so it lines up with York Road, then paving it. The Town's capital report also lists signalization, turn lanes and York Road paving as part of the job. A Town resolution puts Nolensville's local match at an estimated $716,457.
The delay came from the utilities. The Town's August 21 capital projects update marked the project "Delayed" because of utility relocation, including telecommunication lines. It had been scheduled for completion in May 2026, and the contractor was then aiming for late September, pending TDOT's confirmation. Then came the Williams Road closure. TDOT's October 8 notice set it for October 12 through 16 for shoulder work, with local traffic sent in from Clovercroft Road. The Town's video gave October 12 through 15. For the October 20 and 21 paving, the Town expected two lanes open during peak periods, with occasional one-lane flagging.
The Town has not yet published a date for turning on the new signal. Until it does, the late-October paving is the latest public milestone.
The fast intersection and the slow one
Two other intersections on the Town's August list show how wide the range is.
Kidd Road got a temporary traffic signal on wood poles with overhead wiring for $142,420. It ran in flash mode starting July 9, got striping the next day, and was fully activated on July 16, 2026. It moved quickly because nothing had to be bought, moved or realigned.
Rocky Fork Road at Newsome Lane is a permanent project: grading, drainage, signing, striping, paving and traffic signals. The Town has budgeted $288,000 for FY25-26 and $1.712 million for FY26-27. Right-of-way purchases were finished and the bid package went out August 4. The Town received four bids on September 3. Two of them did not include a bid package that complied with state law, and on September 21 the Board of Commissioners rejected all four through Resolution 26-104 and ordered a rebid. Rebids were due October 13, and the resolution calls for the Board to consider a contract award at its November 2026 regular meeting. So the first realistic construction news for Rocky Fork and Newsome comes after that meeting.
A smaller fix is due at Nolensville Road and Rocky Fork Road, where the damaged pedestrian signal is getting a permanent replacement. Delivery of the signal parts takes a long time, and the Town's target is November 2026.
Where the rest of the list stands
Most of Nolensville's other road projects are at even earlier stages. Here is each one's status in the Town's August 21, 2026 update, with the next milestone the Town has posted.
| Project | Stage as of Aug. 21, 2026 | Next posted milestone |
|---|---|---|
| Clovercroft Road widening at Nolensville Road, 3 lanes to 4 | Engineering; field survey done July 17 | Traffic analysis 10/30/26, preliminary plans and estimate 12/31/26 |
| Sunset Road Phase 3 widening | Right-of-way only; 21 of 29 tracts closed | Remaining tracts pending or in negotiation; $1.035M budgeted for FY26-27 |
| Stonebrook sidewalk, Baronswood to Norfolk to Countryside | Surveyor selected; agreement awaiting Board approval | Preliminary design after the survey |
| Sam Donald Court sidewalk | Delayed; materials delivered | Completion projected for end of September 2026 |
| Historic District streetscape | On hold by Board consensus | No date |
Clovercroft is worth following because it's the one widening on the list that is already in design. The Board approved an engineering agreement with STV on June 15, 2026, and the consultant's fee for preliminary engineering is $119,691. A preliminary plan and cost estimate due at the end of December is still a long way from a construction start. Sunset Road Phase 3 is earlier still, because a road can't be designed and built until all 29 property pieces are secured.
The widening, and why 2036 matters
Nolensville Road through the center of town already has some upgrades. A Town resolution credits earlier widening and intersection work between Clovercroft Road and York/Williams, plus a $495,000 project that added a southbound turn lane at Sunset Road. The stretch from Burkitt Road to Sunset Road is the one waiting.
That stretch is now in TDOT's 10-Year Project Plan through the state's Statewide Partnership Program. The state's commitment tops out at $93.5 million, construction is set for 2036, and any costs above that cap fall to the Town or other non-TDOT funding. Under Resolution 26-087, approved August 6, 2026, Nolensville commits $500,000 toward preliminary engineering and $10.5 million toward construction, with a $500,000 deposit due with the signed agreement.
The design is modest: three lanes with curb and gutter on both sides and a 10-foot shared-use path along the west side. In other words, a center turn lane and a path rather than a multi-lane highway through the Historic District. With construction a decade away, the intersections on this page are the improvements you'll drive on in the meantime.
North of Mill Creek, Davidson County moves first
If your commute goes north on Nolensville Pike, the state's own widening is much closer to finishing. TDOT is reconstructing and widening about 6.5 miles of State Route 11, from Old Hickory Boulevard to near Sunset Road, in three phases. Phase I, from near Old Hickory Boulevard to north of Mill Creek in southern Davidson County, is underway. It will have five lanes, bike lanes and sidewalks on both sides, with completion estimated for July 2027.
There are two commute effects listed on TDOT's project page. Barnes Road at Nolensville Pike is tentatively set to close on Monday, October 26 and reopen in March 2027 for utility relocation, an added turn lane onto Nolensville Pike and a right turn lane onto Labrador Lane. Dedicated left-turn lanes from Shane Point to Bradford Hills won't reopen until the project is close to done. Phase III, the part that reaches Nolensville, is the state-and-local partnership described above.
Getting the next notice before you're in the line
Since the big changes are years out, most of what affects your daily drive will be short notices: a two-day paving job, a one-day closure, an intersection shut for a week. In October alone, the Town posted:
- Paving on Baronswood Drive, plus curb and concrete work on Nolen Park Circle and an overlay on Quarterhouse Lane, with traffic sometimes cut to one lane and a request that residents keep cars out of active work areas
- A one-day closure of Rocky Fork Road east of Nolensville Elementary's east entrance on October 16 for tree removal, detoured through Sherwood Green via Sugar Mill Drive, Burris Drive and Petral Drive
- Weekday blasting from 3 to 5 p.m., weather permitting, at Southern Land's Fairington development off McFarlin Road, scheduled for four weeks starting with the October 7 notice
When the Town relaunched its website on September 15, it added optional text alerts for road work, incidents and closures, plus email notifications you can sign up for by topic. The Town news page is where those notices appear first, and the Board's November meeting is where the next intersection, Rocky Fork and Newsome, is expected to get its contractor.
Road projects like these shape how a street works long before they show up in a home's value, and that matters whether you're settling in or thinking about your next move. If you want to know how a specific project near your street could affect a sale or purchase, Robert Young is happy to walk through it with you. Schedule your free market consultation.