East Main Street Bridge Construction in Franklin, TN: Timeline

  • October 8, 2026

Three construction projects now surround Main Street, and they won't finish together. City Hall on the Public Square is set to open in 2027. The Margin District on Columbia Avenue expects residents before the end of 2027 and a grand opening in the first quarter of 2028. The East Main Street Bridge over the Harpeth River has the latest estimate of the three, summer 2028. That means downtown gains a new civic plaza, a one-acre park, a new garage and a new mixed-use block before its main eastern crossing gets back to full width.

The bridge went to one lane each way on September 11, 2026. Since then, crossing the Harpeth into downtown has looked like it will for most of the next two years. The order of what finishes matters more than any single project.

Project Where Status as of early October 2026 Expected finish
East Main Street Bridge replacement State Route 6 over the Harpeth River Phase one: one lane each way, southbound sidewalk closed Summer 2028
New City Hall Public Square block Topped out June 4, 2026 Opening in 2027
The Margin District Between Columbia Avenue and Cummins Street Vertical construction underway; tenants not yet announced Residents before end of 2027; grand opening Q1 2028

The Oldest Structure Finishes Last

The Tennessee Department of Transportation is replacing the bridge, which was built in 1929. Bell & Associates holds the contract. TDOT spokesperson Erin Ziegler told NewsChannel 5 in June that bridges usually last 50 to 80 years. She said this one was still safe and could still carry school buses, and that the state wanted to replace it "before we have to shut the bridge down or lessen it so school buses can't go on it." The new bridge will have four spans instead of the current six.

Here is what's in place now. According to TDOT's September 9 notice, a barrier wall narrows the bridge to one 10-foot travel lane in each direction, each with a one-foot shoulder. The southbound sidewalk is closed. Crews can run intermittent flagging between 9 a.m. and 3 p.m., which leaves the morning and evening commutes alone and puts any delays in the middle of the day. This first phase lasts about a year. Then work moves to the northbound side. If that schedule holds, the switch will come around September 2027.

TDOT's August notice adds two rules for the full project. First, any full closure of the bridge, for work like setting beams, will happen at night and be announced ahead of time. Second, the contractor may not close the Harpeth to recreational use on weekends, and weekday river closures have to be announced in advance. For anyone who paddles this stretch, Saturdays and Sundays stay open the whole time.

The completion date has moved around in coverage. WKRN reported December 2028 in June. NewsChannel 5 said July 2028. TDOT's own August and September notices both say summer 2028, and that's the most recent official estimate. The state points drivers to the TDOT SmartWay map or 511 for current conditions.

TDOT knew the bridge work would land on top of other downtown projects. In June, Ziegler told NewsChannel 5 that the Margin District and the City Hall project had already changed downtown traffic flow. "I didn't realize the amount of local work going on there in Franklin, so we wanna be mindful," she said.

City Hall Is Furthest Along and Adds Parking Under the Square

Of the three projects, the new City Hall is the furthest along. Crews set the final structural beam at a topping-out ceremony on June 4, 2026, after residents had a chance to sign it. The City says the building is slated to open in 2027.

The project covers more than an office building. The City calls it a seven-part redevelopment of the Public Square block:

  • A civic building for about 250 employees, with several public meeting spaces
  • Commercial tenant spaces along 3rd Avenue South
  • A larger plaza on the Square with a pedestrian promenade and full ADA accessibility
  • A one-acre public park with a fountain, seating, gardens and shade trees
  • A 200-space underground parking garage
  • Wider sidewalks and street trees on both sides of 3rd Avenue
  • Expanded public restrooms for downtown

Counting the new garage and the parking already on the block, the City puts the total at more than 500 spaces. Today, its parking page lists the downtown garages on 2nd Avenue South and 4th Avenue South at 300 spaces each. Once City Hall opens, the Square adds a garage that holds two-thirds as many cars as either existing one, plus a park and plaza that give people a new reason to come downtown. With a 2027 opening and a summer 2028 bridge estimate, all of it is scheduled to open while the bridge is still narrowed.

Until then, city business happens elsewhere. The City lists its interim offices at 120 and 204 9th Avenue South, 740 Columbia Avenue, and 507 New Highway 96 West. If you need a permit or a meeting with a city department, check the interim locations page before you head to the Square.

The Margin District Adds Its Own Public Parking

A few blocks south, NAI Nashville Stanton Group is building the Margin District between Columbia Avenue and Cummins Street. The plans call for underground parking with 475 spaces open to the public, retail and commercial space on the first floor, offices on the second, and homes on the third. The developer's June 2025 groundbreaking announcement described 25 condominiums, more than 50,000 square feet of street-level retail and restaurant space, and about 50,000 square feet of office space.

Most longtime residents will know the site by its anchor. Handy Hardware at 731 Columbia Avenue was run by Donna and Andy Willoughby for nearly 50 years. CEO Devin McClendon told the Williamson Herald the building mattered less for its architecture than for its place in the community. Taking it apart turned out to need hand labor, because the 1930s mortar was stronger than the brick. Crews spent months chiseling mortar off by hand, and more than 60 pallets of salvaged brick are now stored off-site. Large structural timbers were saved too. The front of the building will go back to its original look, including the green Spanish tile roof on the front right side and the original front door.

As for timing, the Herald reports that residents should move in before the end of 2027 and the grand opening should come in the first quarter of 2028. NAI plans to announce who will occupy the community gathering space inside the rebuilt hardware building, along with other local and national tenants. No tenants have been named yet.

Between the 200-space City Hall garage and the Margin District's 475 public spaces, downtown is set to gain roughly 675 new garage spaces, all scheduled to open before TDOT expects to finish the bridge.

Walking to Pinkerton Park in the Meantime

With the southbound sidewalk closed, walkers have the clearest reason to rethink their route. TDOT's notice doesn't name a pedestrian detour. In June, NewsChannel 5 reported that both sidewalks will close in the project's second year, so the next phase change will affect walkers too.

There is another crossing that has nothing to do with TDOT's work. According to the City, the Sue Douglas Berry Memorial pedestrian bridge connects downtown with Pinkerton Park. The park is on Murfreesboro Road, with the Harpeth along its west side and Fort Granger to the north. The City's parks guide gives the address as 405 Murfreesboro Road. Across the footbridge you'll find a one-mile paved walking track around the 34-acre park, the Tinkerbell playground next to the parking area, three picnic pavilions, grills and restrooms. The parks department suggests calling its administration office at 615-794-2103 to ask about special events that could overlap with your visit.

Your Downtown Calendar Through 2028

If the current schedules hold, here's how the dates line up. City Hall's opening is given only as 2027, so it could come before or after the bridge's phase change.

  1. September 11, 2026. The East Main Street Bridge narrows to one lane each way, and the southbound sidewalk closes.
  2. About September 2027. Bridge work moves to the northbound side, roughly one year after phase one started.
  3. 2027. City Hall opens with its 200-space garage, one-acre park, larger plaza and public restrooms.
  4. Before the end of 2027. The first Margin District residents move in.
  5. First quarter of 2028. The Margin District grand opening.
  6. Summer 2028. TDOT's estimated finish for the bridge.

All of these dates are estimates, and TDOT notes its work depends on the weather. Five of the six milestones above land before the bridge is done, which means most of downtown's new space opens while its main east-side crossing is still narrowed.

If you're weighing what two years of downtown construction means for your own address, and you'd like to know which phase lines up with a move or a listing you're planning, Robert Young is glad to walk through the timeline with you. Schedule your free market consultation.

Experience You Can Trust

Professional guidance doesn’t have to feel transactional. Robert prioritizes relationships and clarity. Results follow naturally.

Follow Me on Instagram